There are four standard types of dependencies:
- Finish to start (FS)
- A FS B = B can’t start before A is finished, or in another words Activity A must be completed before Activity B can begin.[2]
- (Foundations dug) FS (Concrete poured)
- Finish to finish (FF)
- A FF B = B can’t finish before A is finished or in another words Activity A must be complete before Activity B can finish.[2]
- (Last chapter written) FF (Entire book written)
- Start to start (SS).
- A SS B = B can’t start before A starts or in another words Activity B can start after Activity A has started.[2]
- (Project work started) SS (Project management activities started)
- Start to finish (SF)