Dependency

There are four standard types of dependencies:

  1. Finish to start (FS)
    • A FS B = B can’t start before A is finished, or in another words Activity A must be completed before Activity B can begin.[2]
    • Dependency-FS.png
    • (Foundations dug) FS (Concrete poured)
  2. Finish to finish (FF)
    • A FF B = B can’t finish before A is finished or in another words Activity A must be complete before Activity B can finish.[2]
    • Dependency-FF.png
    • (Last chapter written) FF (Entire book written)
  3. Start to start (SS).
    • A SS B = B can’t start before A starts or in another words Activity B can start after Activity A has started.[2]
    • Dependency-SS.png
    • (Project work started) SS (Project management activities started)
  4. Start to finish (SF)
    • A SF B = B can’t finish before A starts
    • Dependency-SF.png
    • (New shift started) SF (Previous shift finished)
Jan D.
Jan D.

"The only real security that a man will have in this world is a reserve of knowledge, experience, and ability."

Articles: 677

Leave a Reply

Vaše e-mailová adresa nebude zveřejněna. Vyžadované informace jsou označeny *